by Gary Ferguson | Nov 27, 2024
***Addendum 3 changes bid date to 1/16/25.*** Prebid Meeting: Thursday December 19th @ 10am. Meet at project site near the front entrance at Wright Circle Requests for Information (RFIs): Cut off for RFIs is 10 days prior to bid. Liquidated Damages $1,000.00 for each...
by Gary Ferguson | Nov 22, 2024
Site Visit: Wednesday November 27th @ 9am. Meet at BEQ HP505. Special Scheduling: HP505 Renovation must be complete prior to work stating on demo of HP135, HP136, and SHP136A. Requests for Information (RFIs): Cut off for RFIs is Monday, December 9th @ 3pm. Proposal...
by Gary Ferguson | Aug 1, 2023
Special Scheduling Requirements: Demolition of buildings HP305, HP306, and HP309 must be completed before the renovation of BEQ HP165. ***See Pricing Sheet for specific pricing instructions.*** Site Visit: Wednesday, August 9th @ 2pm at HP165. Requests for Information...
by Gary Ferguson | Jul 31, 2023
Site Visit: None Requests for Information (RFIs): Cut off for RFIs is Thursday, August 10th by 5pm. Proposal Acceptance Period: 60 Days from receipt of award Liquidated Damages: $880 for each calendar day of delay until work is completed or...
by Gary Ferguson | May 3, 2023
Site Visit: To be announced via an amendment. ***Per Amendment 1, Wednesday, May 24th @ 2pm. Meet at BEQ HP514.*** Requests for Information (RFI): Cut off for RFIs is Thursday, May 18th @ 2pm. ***Per Amendment 1, cut off date for RFIs has been extended to Wednesday,...